Dubai · 2021

Mina A’Salam, Jumeirah Group

Supply, Installation & Commissioning of Water Source Heat Pump Plant

Mina A’Salam hotel on the Madinat Jumeirah waterway, Dubai

Key findings

  • Hot water generation through 8 x 105kW electric calorifiers
  • 60 m³ daily hot water consumption
  • High energy consumption for domestic water generation
  • Cold water generation through heat exchanger from chilled water system

Key solutions

  • Removal of 1 calorifier, replaced by 2 water source heat pumps
  • Integration of calorifiers and heat pumps with BMS for optimized use rate
  • Domestic hot water generation alongside cold water generation integrated in the chilled water circuit
Improvement workplan
  1. Starting point: COP ≤ 1Hot water generation only
  2. Energy analysis of existing calorifier
  3. Heat pump installation
  4. Hot water & cold water generation
  5. Result: COP hot side ≥ 4; COP cold side ≥ 316% savings · 22 months ROI

Get in touch

+971 4 568 6557

Office address UAE

Energy Savers Technical Services LLC
1103, Opal Tower, Business Bay
Dubai, UAE · PO Box 126723

Office address KSA

Energy Savers Global Company
Office no. 20, Building 8, Al Wurud
Olaya Street, Andalus Mall, Riyadh, KSA
CallWhatsApp